[ProM-developers] Serialization
Dear all,
From now, it is possible to switch off serialization in the ProM ini file. Just add the following lines:
#
# Indicate whether or not ProM should serialize the
# workspace. If switched off, the last serialized
# workspace will be loaded on each start
DO_SERIALIZATION = false
If serialization is switched off, the last serialized workspace will be loaded on every start. This is helpful for debugging purposes.
Please keep in mind that it is necessary to test your work with serialization switched on.
Cheers,
Boudewijn
From now, it is possible to switch off serialization in the ProM ini file. Just add the following lines:
#
# Indicate whether or not ProM should serialize the
# workspace. If switched off, the last serialized
# workspace will be loaded on each start
DO_SERIALIZATION = false
If serialization is switched off, the last serialized workspace will be loaded on every start. This is helpful for debugging purposes.
Please keep in mind that it is necessary to test your work with serialization switched on.
Cheers,
Boudewijn
Joos Buijs
Senior Data Scientist and process mining expert at APG (Dutch pension fund executor).
Previously Assistant Professor in Process Mining at Eindhoven University of Technology
Senior Data Scientist and process mining expert at APG (Dutch pension fund executor).
Previously Assistant Professor in Process Mining at Eindhoven University of Technology
Comments
-
Hi,
seems like this flag is initially "false". At least it was set to false in my fresh installation of 6.2. I was quite surprised after I restarted ProM with an empty workspace. I looked in the ini, found this flag and changed it to "true".
Maybe you have a look at it.
Yours,
Marian
Howdy, Stranger!
Categories
- 1.6K All Categories
- 45 Announcements / News
- 225 Process Mining
- 6 - BPI Challenge 2020
- 9 - BPI Challenge 2019
- 24 - BPI Challenge 2018
- 27 - BPI Challenge 2017
- 8 - BPI Challenge 2016
- 68 Research
- 1K ProM 6
- 394 - Usage
- 288 - Development
- 9 RapidProM
- 1 - Usage
- 7 - Development
- 54 ProM5
- 19 - Usage
- 187 Event Logs
- 32 - ProMimport
- 75 - XESame